30tph Coal Mill Selection Guide

I. Matching capacity requirements with equipment types

For medium capacity requirements of 30 tons/hour (t/h), it is recommended to give priority to medium-speed coal mills (such as ZGM and HP types). Its technical advantages are reflected in:

Grinding efficiency: The roller disc structure can achieve 0-5mm fineness adjustment

Energy consumption index: Unit power consumption is about 7-9kW·h/t, which is better than the 12-15kW·h/t of the ball mill

Space occupied: The vertical structure saves 40% of the space compared with the ball mill


II. Calculation of key selection parameters

Basic parameter verification:

Raw coal characteristics: Hastelloy grindability coefficient HGI ≥ 50

Feed particle size: ≤40mm (matching crushing system required)

Discharge fineness: R90=18-22% (for boiler combustion)

Power configuration formula:

P=K×Q×ln(100/R)

(K=0.15-0.18, Q=30t/h, R=20% when the required power is ≈250kW)

30tph-Coal-Mill.jpg


III. Typical configuration scheme

Component Specifications Requirements Notes Main machine MG113K Grinding disc diameter 2.25m Reducer MLS3626 Output speed 24.5r/min Motor YKK500-4280kW/6kV


IV. System matching suggestions

Dust removal equipment: Pulse bag dust collector (air volume ≥ 15000m³/h)

Monitoring system: Vibration and temperature dual protection devices are required

Wear-resistant parts life: Grinding roller surfacing cycle ≥ 8000 hours

Note: The actual selection should be corrected in combination with the coal quality test report. High-sulfur coal (St,d>2%) requires special anti-corrosion treatment